ONGOING MAJOR CONTRACTS As of June 2006 |
|||||||
PROJECT/FINANCING INSTITUTION CONTRACT NUMBER/DESCRIPTION/CONTRACTOR |
CONTRACT AMOUNT (P' Mil) |
IMPLEMENTATION SCHEDULE |
STATUS |
||||
PHYSICAL (%) |
FINANCIAL (P' Mil.) |
||||||
LOWER AGUSAN DEV. PROJECT-IC/JBIC LADPI-C-1, PACKAGE II, Supplemental Contract No. 1, Construction of LAteral D Sta. 1+400 to Sta. 6+600/P.L. Sebastian Construction |
Original | 72.06 | Start | 01-Aug-03 | Target | 100.00 | |
Revised | 87.69 | Completion | 03-Feb-06 | Actual | 100.00 | 79.32 | |
Variance | 0 | ||||||
Remarks: For acceptance | |||||||
LOWER AGUSAN DEV. PROJECT-IC/JBIC LADPI-C-1, SCHEDULE II, PACKAGE II, Construction of Main Canal for Aupagan Area and Regulating Pond/Concepcion Basic Builders/Kane Construction, Inc. (Joint Venture) |
Original | 210.01 | Start | 26-Nov-98 | Target | 100.00 | |
Revised | 284.85 | Completion | 31-Oct-05 | Actual | 100.00 | 306.70 | |
Variance | 0 | ||||||
Remarks: For acceptance. | |||||||
LOWER AGUSAN DEV. PROJECT-IC/JBIC LADPI-C-1, Schedule II, PACKAGE II, Supplemental Contract No. 1, Construction of Laterals A, B, C, E and F and Sub-Laterals E-1 and E-2/Concepcion Basic Builders/Kane Construction, Inc. (Joint Venture) |
Original | 56.53 | Start | 04-Apr-02 | Target | 100.00 | |
Revised | 60.91 | Completion | 04-Apr-06 | Actual | 100.00 | 58.13 | |
Variance | 0 | ||||||
Remarks: All remaining works requested for deletion. | |||||||
BOHOL IRRIGATION PROJECT-STAGE II/JBIC BHIP2-C-1, Construction of Bayongan Dam and Appurtenant Facilities with Supply, Delivery and Installation of Steel Gates/valves and Discharge Pipes/Hanjin-Kurimoto Joint Venture |
Original | 1,485.91 | Start | 12-Aug-03 | Target | 79.27 | |
Revised | 1,561.39 | Completion | 24-Apr-07 | Actual | 86.11 | 1,042.50 | |
Variance | 6.84 | ||||||
Remarks: Construction on-going. | |||||||
BOHOL IRRIGATION PROJECT-STAGE II/JBIC BHIP2-C-2, Construction of Irrigation Canals and Appurtenant Structures/tHanjin Heavy Industries & Const. Co., LTD. |
Original | 575.83 | Start | 20-Feb-04 | Target | 63.41 | |
Revised | - | Completion | 04-May-07 | Actual | 59.30 |
226.89 |
|
Variance | -4.11 | ||||||
Remarks: Construction on-going. | |||||||
CASECNAN MULTIPURPOSE IRRIG. & POWER PROJ./JBIC CMIPPI-C-S1, Construction of PRIS New Intake, Super Diversion Canal and Related Structures and Supply and Installation of Gates for CMIPP-IC/TOYO-OBAYASHI-UBE Joint Venture |
Original | 688.00 | Start | 12-Sep-03 | Target | 100.00 | |
Revised | 737.28 | Completion | 09-Mar-06 | Actual | 100.00 | 676.00 | |
Variance | 1.36 | ||||||
Remarks: Completed and accepted November 30, 2005. | |||||||
CASECNAN MULTIPURPOSE IRRIG. & POWER PROJ./JBIC CMIPPI-C-S2, Construction of Super Diversion Canal (Sta. 19+200-Sta. 26+600), Laterals A to E and Related Structures and Supply and Installation of Gates for CMIPP-IC/China Geo Engineering (PHIL) Corp. |
Original | 1,108.22 | Start | 23-Feb-04 | Target | 71.90 | |
Revised | - | Completion | 09-May-07 | Actual | 74.11 | 576.43 | |
Variance | 2.21 | ||||||
Remarks: Contract works ong-oing. | |||||||
CASECNAN MULTIPURPOSE IRRIG. & POWER PROJ./JBIC CMIPPI-C-S3, Construction of Super Diversion Canal (Sta. 26+600 to Sta. 29+240) Laterals "E" to "G" and Related Structures and Supply and Installation of Gates for CMIPP-C-S3//TOYO CONSTRUCTION CO. LTD. |
Original | 506.08 | Start | 8-MAR-06 | Target | 4.94 | |
Revised | - | Completion | 6-JAN-08 | Actual | 12.13 | ||
Variance | 7.19 | ||||||
Remarks: Contract work on-going | |||||||
CASECNAN MULTIPURPOSE IRRIG. & POWER PROJ./JBIC CMIPPI-C-U1, PBRIS New Intake, Diversion canal No. 2 (DC-2), PBRIS Main Canal and Related Structures and Supply and installation of Gates for CMIPP-IC/China Intenational Water & Electric Corporation. |
Original | 448.15 | Start | 8-Feb-06 | Target | 16.31 | |
Revised | - | Completion | 7-Jun-07 | Actual | 15.12 | ||
Variance | -1.19 | ||||||
Remarks: Contract work on-going | |||||||
CASECNAN MULTIPURPOSE IRRIG. & POWER PROJ./JBIC CMIPPI-C-U2, Rehabilitation and Improvement of PENRIS Diversion Dam, PBRIS Main Canal and Related Structures and Supply and installation of Gates for CMIPP-IC/China State Construction Engineering Corp. |
Original | 608.64 | Start | 22-Apr-04 | Target | 52.47 | |
Revised | - | Completion | 18-Oct-06 | Actual | 54.06 | 232.15 | |
Variance | 1.59 | ||||||
Remarks: Contract work on-going | |||||||
SOUTHERN PHIL IRRIGATION SECTOR PROJECT/ADB SPISPI-C-1, Construction of Can-asujan Dam and Appurtenant Facilities/China Electric Power Technology Import and Export Corp. |
Original | 265.83 | Start | 30-Jul-03 | Target | 100.00 | |
Revised | 285.69 | Completion | 14-May-06 | Actual | 100.00 | 279.87 | |
Variance | 0 | ||||||
Remarks: accepted May 12, 2006 | |||||||
BALOG-BALOG MULTIPURPOSE PROJECT/Locally Funded BBMPD-C-3, Construction of North Main Canal/A.M. Oreta & Co., Inc. |
Original | 757.1 | Start | 18-Jan-00 | Target | 100.00 | |
Revised | 582.3 | Completion | 21-Mar-06 | Actual | 65.31 |
357.21 |
|
Variance | -34.69 | ||||||
Remarks: Construction works is on-going. ROW problems still exist on 1+600 to 1+800; 8+680 to 12+900 and 15+800 to 16+427 due to non-payment of land acquisition. Implementaion of the approval of Supplemental Contract No. 1 was deffrred due to lack of funds. | |||||||
ADDALAM RIVER IRRIGATION PROJECT/Locally Funded ADRIPD-C-1 Construction of Addalam Diversion Dam and intake Barrel for Addalam River IP/Atlantic Erectors Inc./Brostan Const. Development Corp. (Joint Venture) |
Original | 147.246 | Start | 05-Oct-01 | Target | 100.00 | |
Revised | 232.105 | Completion | 3-Aug-06 | Actual | 90.32 |
188.45 |
|
Variance | -9.68 | ||||||
Remarks: Request for additional time extension equivalent to 112 calendar days is still at NIA-CO for approval. | |||||||
ADDALAM RIVER IRRIGATION PROJECT/Locally Funded ADRIP-C-1 Construction of Main Canal, Laterals and Appurtenant Structure for Addalam River IP/Atlantic Erectors Inc./Brostan Const. Development Corp. (Joint Venture) |
Original | 73.392 | Start | 29-Jun-05 | Target | 99.06 | |
Revised | Completion | 6-Sep-06 | Actual | 24.37 |
150.46 |
||
Variance | -74.69 | ||||||
Remarks: Request for additional time extension equivalent to 66 calendar days is still at NIA-CO for approval. | |||||||
NIA-Central Office Covered Court/Locally Funded, NIA-CO-C-1-04, Construction of NIA Central Office Covered Court/Abueva Konstruct and Development Corporation | Original | 6.660 | Start | 31-Aug-05 | Target | 100.00 | |
Revised | Completion | 15-May-06 | Actual | 100.00 |
6.47 |
||
Variance | 0 | ||||||
Remarks: For acceptance. | |||||||
SMALL RESERVOIR IRRIGATION PROJECT/Locally Funded SRIP-C-14, Construction of Aulo Small Reservoir Irrigation Project/R.N. Guico Construction and Development |
Original | 159.998 | Start | 05-Jun-01 | Target | 100.00 | |
Revised | 175.672 | Completion | 11-Apr-06 | Actual | 100.00 |
157.85 |
|
Variance | -2.50 | ||||||
Remarks: Construction works ongoing. | |||||||
BANAOANG PUMP IRRIGATION PROJECT/Built Transfer Project, BT-001-02, Banaoang Pump Irrigation Project/China National Constructional and Agricultural Machinery Import and Export | Original | $ 34.98 | Start | 06-Mar-03 | Target | 28.10 | |
Revised | - | Completion | 05-Jan-08 | Actual | 24.73 |
$ 7.84 |
|
Variance | 16.14 | ||||||
Remarks: Field survey and sub-soil investigation and design works ongoing | |||||||
BANAOANG PUMP IRRIGATION PROJECT/Built Transfer Project, BT-001-02, Package "A" Site Survey, Sub-soil Investigation and Detailed Engineering /China National Constructional and Agricultural Machinery Import and Export | Original | $ 3.07 | Start | Target | 100.00 | ||
Revised | - | Completion | Actual | 100.00 |
$ 3.07 |
||
Variance | 0 | ||||||
Remarks: Completed and accepted last March 29, 2005 | |||||||
BANAOANG PUMP IRRIGATION PROJECT/Built Transfer Project, BT-001-02, Package "B" Engineering Procurement and Construction /China National Constructional and Agricultural Machinery Import and Export | Original | $ 31.91 | Start | Target | 34.04 | ||
Revised | - | Completion | Actual | 32.61 |
$ 4.77 |
||
Variance | -1.43 | ||||||
Remarks Construction Works is on-going | |||||||