ONGOING MAJOR CONTRACTS

As of June 2006

PROJECT/FINANCING INSTITUTION

CONTRACT NUMBER/DESCRIPTION/CONTRACTOR

CONTRACT AMOUNT  (P' Mil)

IMPLEMENTATION

SCHEDULE

STATUS

PHYSICAL (%)

FINANCIAL (P' Mil.)

LOWER AGUSAN DEV. PROJECT-IC/JBIC

LADPI-C-1, PACKAGE II, Supplemental Contract No. 1, Construction of LAteral D Sta. 1+400 to Sta. 6+600/P.L. Sebastian Construction

Original 72.06 Start 01-Aug-03 Target 100.00  
Revised 87.69 Completion 03-Feb-06 Actual 100.00 79.32
        Variance 0  
Remarks: For acceptance

LOWER AGUSAN DEV. PROJECT-IC/JBIC

LADPI-C-1, SCHEDULE II, PACKAGE II, Construction of

Main Canal for Aupagan Area and Regulating Pond/Concepcion Basic Builders/Kane Construction, Inc. (Joint Venture)

Original 210.01 Start 26-Nov-98 Target 100.00  
Revised 284.85 Completion 31-Oct-05 Actual 100.00 306.70
        Variance 0  
Remarks: For acceptance.

LOWER AGUSAN DEV. PROJECT-IC/JBIC

LADPI-C-1, Schedule II, PACKAGE II, Supplemental Contract No. 1, Construction of Laterals A, B, C, E and F and Sub-Laterals E-1 and E-2/Concepcion Basic Builders/Kane Construction, Inc. (Joint Venture)

Original 56.53 Start 04-Apr-02 Target 100.00  
Revised 60.91 Completion 04-Apr-06 Actual 100.00 58.13
        Variance 0  
Remarks: All remaining works requested for deletion.
BOHOL IRRIGATION PROJECT-STAGE II/JBIC

BHIP2-C-1, Construction of Bayongan Dam and Appurtenant Facilities with Supply, Delivery and Installation of Steel Gates/valves and Discharge Pipes/Hanjin-Kurimoto Joint Venture

Original 1,485.91 Start 12-Aug-03 Target 79.27  
Revised 1,561.39 Completion 24-Apr-07 Actual 86.11 1,042.50
        Variance 6.84  
Remarks: Construction on-going.
BOHOL IRRIGATION PROJECT-STAGE II/JBIC

BHIP2-C-2, Construction of Irrigation Canals and Appurtenant Structures/tHanjin Heavy Industries & Const. Co., LTD.

Original 575.83 Start 20-Feb-04 Target 63.41  
Revised - Completion 04-May-07 Actual 59.30

226.89

        Variance -4.11  
Remarks: Construction on-going.
CASECNAN MULTIPURPOSE IRRIG. & POWER PROJ./JBIC

CMIPPI-C-S1, Construction of PRIS New Intake, Super Diversion Canal and Related Structures and Supply and Installation of Gates for CMIPP-IC/TOYO-OBAYASHI-UBE Joint Venture

Original 688.00 Start 12-Sep-03 Target 100.00  
Revised 737.28 Completion 09-Mar-06 Actual 100.00 676.00
        Variance 1.36  
Remarks: Completed and accepted November 30, 2005.
CASECNAN MULTIPURPOSE IRRIG. & POWER PROJ./JBIC

CMIPPI-C-S2, Construction of Super Diversion Canal (Sta. 19+200-Sta. 26+600), Laterals A to E and Related Structures and Supply and Installation of Gates for CMIPP-IC/China Geo Engineering (PHIL) Corp.

Original 1,108.22 Start 23-Feb-04 Target 71.90  
Revised - Completion 09-May-07 Actual 74.11 576.43
        Variance 2.21  
Remarks: Contract works ong-oing.
CASECNAN MULTIPURPOSE IRRIG. & POWER PROJ./JBIC

CMIPPI-C-S3, Construction of Super Diversion Canal (Sta. 26+600 to Sta. 29+240) Laterals "E" to "G" and Related Structures and Supply and Installation of Gates for CMIPP-C-S3//TOYO CONSTRUCTION CO. LTD.

Original 506.08 Start 8-MAR-06 Target 4.94  
Revised - Completion 6-JAN-08 Actual 12.13  
        Variance 7.19  
Remarks: Contract work on-going
CASECNAN MULTIPURPOSE IRRIG. & POWER PROJ./JBIC

CMIPPI-C-U1, PBRIS New Intake, Diversion canal No. 2 (DC-2), PBRIS Main Canal and Related Structures and Supply and installation of Gates for CMIPP-IC/China Intenational Water & Electric Corporation.

Original 448.15 Start 8-Feb-06 Target 16.31  
Revised - Completion 7-Jun-07 Actual 15.12  
        Variance -1.19  
Remarks: Contract work on-going
CASECNAN MULTIPURPOSE IRRIG. & POWER PROJ./JBIC

CMIPPI-C-U2, Rehabilitation and Improvement of PENRIS Diversion Dam, PBRIS Main Canal and Related Structures and Supply and installation of Gates for CMIPP-IC/China State Construction Engineering Corp.

Original 608.64 Start 22-Apr-04 Target 52.47  
Revised - Completion 18-Oct-06 Actual 54.06 232.15
        Variance 1.59  
Remarks: Contract work on-going
SOUTHERN PHIL IRRIGATION SECTOR PROJECT/ADB

SPISPI-C-1, Construction of Can-asujan Dam and Appurtenant Facilities/China Electric Power Technology Import and Export Corp.

Original 265.83 Start 30-Jul-03 Target 100.00  
Revised 285.69 Completion 14-May-06 Actual 100.00 279.87
        Variance 0  
Remarks: accepted May 12, 2006
BALOG-BALOG MULTIPURPOSE PROJECT/Locally Funded

BBMPD-C-3, Construction of North Main Canal/A.M. Oreta & Co., Inc.

Original 757.1 Start 18-Jan-00 Target 100.00  
Revised 582.3 Completion 21-Mar-06 Actual 65.31

357.21

        Variance -34.69  
Remarks: Construction works is on-going. ROW problems still exist on 1+600 to 1+800; 8+680 to 12+900 and 15+800 to 16+427 due to non-payment of land acquisition. Implementaion of the approval of Supplemental Contract No. 1 was deffrred due to lack of funds.
ADDALAM RIVER IRRIGATION PROJECT/Locally Funded

ADRIPD-C-1 Construction of Addalam Diversion Dam and intake Barrel for Addalam River IP/Atlantic Erectors Inc./Brostan Const. Development Corp. (Joint Venture)

Original 147.246 Start 05-Oct-01 Target 100.00  
Revised 232.105 Completion 3-Aug-06 Actual 90.32

188.45

        Variance -9.68  
Remarks: Request for additional time extension equivalent to 112 calendar days is still at NIA-CO for approval.
ADDALAM RIVER IRRIGATION PROJECT/Locally Funded

ADRIP-C-1 Construction of Main Canal, Laterals and Appurtenant Structure for Addalam River IP/Atlantic Erectors Inc./Brostan Const. Development Corp. (Joint Venture)

Original 73.392 Start 29-Jun-05 Target 99.06  
Revised   Completion 6-Sep-06 Actual 24.37

150.46

        Variance -74.69  
Remarks: Request for additional time extension equivalent to 66 calendar days is still at NIA-CO for approval.
NIA-Central Office Covered Court/Locally Funded, NIA-CO-C-1-04, Construction of NIA Central Office Covered Court/Abueva Konstruct and Development Corporation Original 6.660 Start 31-Aug-05 Target 100.00  
Revised   Completion 15-May-06 Actual 100.00

6.47

        Variance 0  
Remarks: For acceptance.
SMALL RESERVOIR IRRIGATION PROJECT/Locally Funded

SRIP-C-14, Construction of Aulo Small Reservoir Irrigation Project/R.N. Guico Construction and Development

Original 159.998 Start 05-Jun-01 Target 100.00  
Revised 175.672 Completion 11-Apr-06 Actual 100.00

157.85

        Variance -2.50  
Remarks: Construction works ongoing.
BANAOANG PUMP IRRIGATION PROJECT/Built Transfer Project, BT-001-02, Banaoang Pump Irrigation Project/China National Constructional and Agricultural Machinery Import and Export Original $ 34.98 Start 06-Mar-03 Target 28.10  
Revised - Completion 05-Jan-08 Actual 24.73

$ 7.84

        Variance 16.14  
Remarks: Field survey and sub-soil investigation and design works ongoing
BANAOANG PUMP IRRIGATION PROJECT/Built Transfer Project, BT-001-02, Package "A" Site Survey, Sub-soil Investigation and Detailed Engineering /China National Constructional and Agricultural Machinery Import and Export Original $ 3.07 Start   Target 100.00  
Revised - Completion   Actual 100.00

$ 3.07

        Variance 0  
Remarks: Completed and accepted last March 29, 2005
BANAOANG PUMP IRRIGATION PROJECT/Built Transfer Project, BT-001-02, Package "B" Engineering Procurement and Construction /China National Constructional and Agricultural Machinery Import and Export Original $ 31.91 Start   Target 34.04  
Revised - Completion   Actual 32.61

$ 4.77

        Variance -1.43  
Remarks Construction Works is on-going
               

Top ^

Last update : Monday, 14 August 2006

 

Email us at yulcb@lycos.com  