BOHOL IRRIGATION PROJECT - STAGE II (BIP-II)

 

Project Profile : 

Location:

Ubay, San Miguel, and Trinidad in Bohol

Project Description:

  1. Construction of the following:

    1. 0.8 km. diversion canal from Sta.16+880 of the BHIP-I Main canal to the proposed reservoir of Bayongan Dam.

    2. 34.5 m. high earth fill dam across Bayongan River.

    3. Main Canal (12.7 km) interconnecting the Bayongan reservoir with the Capayas reservoir.

    4. Lateral Canal, (49.7km.) drainage and road network in the 4,550 ha. comprising of 4,140 ha. in. the Bayongan system and 410 ha.of an extension area in the Capayas  System with existing area of 750 ha. Lateral Canal (18.0 km.), Drainage Canals (65.3 km.).

  2. Development of on-farm facilities including land development.

  3. Relocation and/or resettlement of families (about 268 families) affected by the dam  construction and reservoir.

  4. Water management plan including water measurement and communication network.

 

Project Data:
Financing Institution : Japan Bank for International Cooperation (JBIC)
Loan Number : PH-P202
Amount of Loan  : 6.078 Billion Yen
Project Cost   P2,384.4 Million
Effectivity Date : March 28, 2000
Loan Closing Date : March 28, 2008
Date Signed : December 28, 1999
Rate of Interest : 1.80% per annum (Principal I) 0.75% per annum (Principal II)
Terms : 20 years
Target Beneficiaries : 1,635 farm families
Date Started : January 1, 2000
Completion Date : December 31, 2005

 

Last update : Wednesday, 09 August 2006

 